SRDPL is committed to control accidents at its construction sites through constant awareness on preventive measures & Providing Personal Protective Equipment (PPE). The health, safety, welfare of our employees and labours is our prime importance to our company.

SAFETY COMMITTE
- 1) It includes, site PM/QAE/Store keeper/Safety officer.
- 2) A safety officer is certified by renown organisation.
- 3) Monthly meeting are held at site & Minutes of the meeting are sent to HO.
- 4) Safety officer to conduct daily toolbox session and awareness session per week.
- 5) Safety representative displays a list of emergency contacts on notice board.
PPE (Personal Protective Equipment):
- 1) Safety helmet, jacket, shoes are must in working premises.
- 2) Safety belt to be used while working on heights.
- 3) Hand gloves to be used for material handling.
- 4) Safety goggle to be used while welding, grinding, concrete breaking etc.
- 5) Gumboots to be used for concrete work.
- 6) First Aid kit to be kept in store all the time.
Equipment safety:
- 1) Only trained operators to handle equipment.
- 2) Loose wires will not be inserted in sockets.
- 3) Covered switchboard to be installed outdoors.
- 4) All equipment’s to be cleaned after use.

Equipment safety:
- Excavation:
- Barricade the excavated area by barricading tapes.
- Hard Barricading in deep excavation areas.
- Concreting in Foundations:
- Shoring and strutting of trench/pit.
- Concreting in Foundations:
- Shoring and strutting of trench/pit.
- Slab Form Work:
- Fix props truly vertical with proper bracing.
- Centre steel span pin to be tightened properly.
- Attendant is must where material are likely to fall.
- Concreting of Slab:
- Ensure the lift scaffolding installed vertical.
- Do not throw of unused materials from upper floors.
- Walkways to be used on slab reinforcement to walk.
- Welding:
- Barricade the working area
- Welding work should be away from damp area.
- Temporary cables shall be installed at heights.
- Cable joints shall be properly insulated.
- Welding work should be done using gloves and protective gears.
- Masonry & Plaster:
- Throwing of waste material shall be avoided.
- Scaffolding shall be sturdy & properly braced.
- Housekeeping:
- Empty cement bags shall be stacked properly.
- All shuttering material to be stacked in define areas.
- Neatness & cleanliness shall be maintained on entire site.
- Mandatory:
- Use of hooked safety belts when working on height.
- Use of helmets is must while on site.